7th January 2021 /// Project Update….. TM3 Airports continue to support and advise daa plc on the development of its air traffic management and ALCMS (airfield lighting control system).
Project: To Implement the ALCMS / ILCMS System Roadmap
SCOPE:
The project includes for the preparation of documentation for separate contract lots to appoint two framework contractors to proceed with works as outlined in the Dublin Airport AGL Control and Monitoring System roadmap.
Contract Lot 1 is to upgrade the ALCMS and is split into 3 different phases:
Phase 1
Modifications to the ALCMS to allow the integration of the new IAA Control Tower into the Airfield Lighting Control and Monitoring system including integrating the existing A-SMGCS system and the new IRVR equipment.
Phase 2
Modifications to the ALCMS to allow the integration of the replacement airfield Substation T fitted with series communication controlled and monitored CCR’s.
Phase 3
Modifications to the ALCMS to allow the integration of the new substations associated with the new Northern Parallel Runway development.
Contract Lot 2
Design and implementation of an ILCMS system. Initially comprising a trial installation to be monitored and assessed over a period of time, the overall plan is to rollout the implementation of ILCMS as the ALCMS phases outlined above are executed.
Contracted by Dublin Airport Authority (daa) as the Principal Consultants to produce a roadmap for the development strategy of the Dublin Airport ALCMS to meet the requirements of current airfield developments including a new IAA Control Tower and the new Northern Parallel Runway. The strategy also had to include the future proofing of the system for possible future development to a higher level of A-SMGCS or a Follow-the-Green type system.
This was a great project to be involved in.